Repair Work Notice: 

Dear visitors, our shopping center remain open and accessible during parking lot renovation works.

In additional to fixing divits, potholes, we are re-doing all the speedbumps in our 6 entrances.  Parking lot work will take place over different days and weeks to ensure:  1) there will be an accessible entrance on both Bellaire Blvd and Ranchester St;  2)  all stores remain accessible at all time; and 3) parking spaces will not be compromised on peak traffic days (Fri, Sat & Sun).

We are re-doing our high traffic back parking lot entrance on Ranchester St from asphalt to concrete to better handle the load of pass-through traffic.  The concrete replacement require rebar and curing time, thus the Ranchester back parking lot entrance will be shut off for several days (Thurs Apr 18th to Mon Apr 22nd).  During this time, the back parking lot can be access via the Bellaire entrance located at 9102 Bellaire Blvd.

Few sizeable sections will be blocked off for asphalt works:  1) We will also be redoing the concrete ramp and accessible spaces near the 9108 Bellaire area.  2) We will be redoing the accessibility spaces by Welcome storefront in front of Evergreen Pharmacy.  3) We will be redoing the accessbility space by 9110B and 9110C facing Ranchester.

We apologize for any inconvenience caused during this period and we thank you for your understanding.

***

Status Update (5/3/2024):

  • Speedbumps on both Bellaire entrances completed.  Both Bellaire entrances now open.
  • Speedbump on Ranchester by Artisan 360 completed and now opens.
  • Ranchester back parking lot entrance concrete work and asphalt work completed (Apr 18-Apr 21st).  Entrance opens.
  • Bellaire back parking lot entrance/exit asphalt work completed.  Entrance now opens.
  • 9108 area concrete ramp and accessible parking spaces repair work started on Tues Apr 23rd and completed.  Accessibility spaces re-open.
  • Accessibility spaces on the left entrance of Welcome Supermarket asphalt work completed.  Accessibility spaces re-open.
  • 1 main entrance repair work yet to be done – Ranchester entrance by Dentist 101.
  • 9110B storefront accessible parking space to be relocated for easier accessibility.  Work to take place soon.